Am very busy at the moment as all of our projects are either in construction or in the case of Lake Villas being finished off. Lake Villas is looking really good now, we have quite a few residents and are putting the final touches to the furniture in the remaining units. Will have to start thinking about updating the website before long, and at last we have got planning permission to extend and develop the shower room by the pool into a full 2 storey clubhouse with a bar, restaurant and gymnasium. We have just finished the minimart and that will be open in few weeks and the minibus will be ready to operate in the next high season.
The construction at Phoenix Grove is going well, the first phase I am happy to say will be finished in December and the whole project should be done by July 2009.
Emerald Palace is a little bit behind schedule at the moment due to the recent spell of bad weather but we are confident that we can make up the time before the finish date in October.

Richard Haughton